A+ Exams, A+ Certificate
QUESTION NO: 1
A qualitative analysis identified a server crash as an internal project risk with a medium probability and high adverse impact to the project. The project manager decides to manage this risk by authorizing the purchase and installation of a tape backup unit for the server, to prevent the potential loss of documents. Which of the following risk response strategies was applied in this circumstance? A+ Exams
A. Acceptance
B. Transfer
C. Mitigation
D. Avoidance
Answer: A
QUESTION NO: 2
A project has been delayed due to an ongoing labor dispute. The project sponsor asks the project manager to transfer the risk to complete the project on time. Which of the following is a method of transferring the risk?
A. Delay the project
B. Change the project schedule
C. Outsource the project
D. Hire more resources
Answer: C
QUESTION NO: 3
ASPI of 1.1 means that the project Is:
A. under-budget.
B. behind schedule.
C. ahead of schedule.
D. over-budget.
Answer: A
QUESTION NO: 4
Which of the following is the BEST reason to conduct a feasibility analysis?
A. To ensure that risks are addressed during the project
B. To authorize a project
C. To gather technical data
D. To assign team member roles
Answer: C
QUESTION NO: 5
Which of the following is the BEST definition of a stakeholder? (Select TWO). A+ Certificate
A. Anyone impacted negatively by the project.
B. Anyone who is in the company where the project is taking place.
C. Anyone who is interested in the project.
D. Anyone who negatively impacts the project.
E. Anyone impacted positively by the project.
Answer: C
QUESTION NO: 6
Which of the following is a characteristic of a project charter?
A. Issued by the project manager with support from the project sponsor.
B. Links the project to the on-going work of the organization through a business plan.
C. Formally recognizes the existence or establishment of the project.
D. Provides low-level requirements for the project.
Answer: C