QUESTION NO: 1

A qualitative analysis identified a server crash as an internal project risk with a medium probability and high adverse impact to the project. The project manager decides to manage this risk by authorizing the purchase and installation of a tape backup unit for the server, to prevent the potential loss of documents. Which of the following risk response strategies was applied in this circumstance? A+ Exams

A. Acceptance
B. Transfer
C. Mitigation
D. Avoidance
Answer: A

QUESTION NO: 2
A project has been delayed due to an ongoing labor dispute. The project sponsor asks the project manager to transfer the risk to complete the project on time. Which of the following is a method of transferring the risk?
A. Delay the project
B. Change the project schedule
C. Outsource the project
D. Hire more resources
Answer: C

QUESTION NO: 3
ASPI of 1.1 means that the project Is:
A. under-budget.
B. behind schedule.
C. ahead of schedule.
D. over-budget.
Answer: A

QUESTION NO: 4
Which of the following is the BEST reason to conduct a feasibility analysis?
A. To ensure that risks are addressed during the project
B. To authorize a project
C. To gather technical data
D. To assign team member roles
Answer: C

QUESTION NO: 5
Which of the following is the BEST definition of a stakeholder? (Select TWO). A+ Certificate

A. Anyone impacted negatively by the project.
B. Anyone who is in the company where the project is taking place.
C. Anyone who is interested in the project.
D. Anyone who negatively impacts the project.
E. Anyone impacted positively by the project.
Answer: C

QUESTION NO: 6
Which of the following is a characteristic of a project charter?
A. Issued by the project manager with support from the project sponsor.
B. Links the project to the on-going work of the organization through a business plan.
C. Formally recognizes the existence or establishment of the project.
D. Provides low-level requirements for the project.
Answer: C

CompTIA A+ Certification, 220-701

QUESTION NO: 1
A project manager has a project with staff in four different countries. When generating the resource management plan, which of the following should be considered FIRST?
A. Reviewing holiday and vacation schedule with all team members.
B. Getting the email address of all the employees.
C. Locating each employee on the map in the office.
D. Understanding the International country code of all the team members.
Answer: C
QUESTION NO: 148
Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?
A. Exploiting
B. Crashing
C. Optimizing
D. Fast tracking
Answer: D

QUESTION NO: 2
Two team members refuse to work together and have undermined the project with their constant bickering. The project manager needs both of them to complete the project. The team members meet and agree to work at different times. Which of the following conflict resolution styles is being used?
A. Forcing
B. Smoothing
C. Confronting
D. Compromising
Answer: D
QUESTION NO: 150
A project manager creates a detailed list of costs for each activity involved in the project and then uses the sum of the individual activities to create the budget. Which of the following cost estimating techniques was used?
A. Bottom-up
B. Expert judgment
C. Parametric
D. Top-down
Answer: A
Topic 4, Volume D

QUESTION NO: 3
A project team has increased from six to twelve resources. How many total communication paths exist after the addition of resources?
A. 24
B. 48
C. 66
D. 144
Answer: C

QUESTION NO: 4
Which of the following is included in the project scope document? (Select TWO).
A. Quality metrics
B. Work packages
C. Assumptions
D. Constraints
E. Resource requirements
Answer: B, E

QUESTION NO: 5

A project manager has finished the first phase of a project. Who of the following determines if the project continues?
A. End users
B. Project manager
C. Project team
D. Project sponsor

Answer: D

Topics on A+ Exams, CompTIA A+ Certification

Topic 3, Volume C
QUESTION NO: 1
If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?
A. -$1,000
B. $1,000
C. -$3,000
D. $3,000
Answer: B

QUESTION NO: 2
After a change control Board meeting, which of the following actions should the project manager do NEXT?
A. Notify the requester of the verdict.
B. Review the impact of proposed change.
C. Update the project scope statement.
D. Document the specific change request.
Answer: D

QUESTION NO: 3
Changing the project schedule to prevent a known risk is an example of which of the following risk responses?
A. Mitigation
B. Avoidance
C. Acceptance
D. Transference
Answer: B

QUESTION NO: 4
The purpose of the WBS is to:
A. maintain standards compliance.
B. manage change requests.
C. determine work packages.
D. aid in version control.

Answer: C
QUESTION NO: 5
Which of the following would be the MOST important objective of a kick-off meeting? (Select TWO).
A. To educate team members on what will be expected
B. To give official notification for the project
C. To inform the project sponsor on what will be expected
D. To create a work breakdown structure (WBS)
E. To develop the statement of work (SOW)
Answer: A, C

QUESTION NO: 6
Which of the following components is included in a transition plan?
A. Ownership
B. Quality metrics
C. Project budget
D. Quality baseline
Answer: A, D

QUESTION NO: 7
Which of the following is the BEST point for a project manager to join a project?
A. Project initiation
B. Project pre-planning
C. Project planning
D. Project executing
Answer: B

QUESTION NO: 8
Which of the following is the BEST point for a project manager to join a project? A+ Exams

A. Project initiation
B. Project pre-planning
C. Project planning
D. Project executing
Answer: B

A+ Exams, practise and the answers

QUESTION NO: 1

A new Samba server (Version 3) has been setup with a brand new colour laser printer. The printer is attached to the parallel port and is setup using CUPS. What share must you setup in your smb.conf file to allow client computers to download the new drivers?

A. [printers]

B. [print$]

C. [printer$]

D. [cups$]

Answer: B

QUESTION NO: 2

The SAMBADOM domain has been added as a trusted account to an existing domain called WIN3K. Which command should be run on the Samba server in order to establish the trusted relationship to the WIN3K domain?

A. net rpc trustdom add WIN3K

B. net rpc addtrust WIN3K

C. net rpc trustdom establish WIN3K

D. net rpc trustdom establish SAMBA

Answer: C

QUESTION NO: 3

By default, on what port does SWAT listen?

A. 901

Answer: A

QUESTION NO: 4

By specifying the _________ parameter in smb.conf and assigning it an appropriate value, Samba will create Machine Trust Accounts automatically when the client joins the domain.

A. ADDMACHINESCRIPT

Answer: A

QUESTION NO: 5

Which command typed on a Samba 3 server will print out the local SID?

A. net get sid localhost

B. net getlocalsid

C. net getsid

D. net rpc get localsid

Answer: B

QUESTION NO: 6

What command will test the file /root/smb.conf for internal correctness? (Enter the command and any required options or parameters)

A. TESTPARM/ROOT/SMB.CONF

Answer: A

QUESTION NO: 7

When a Windows domain controller is used, which of the following is assigned a Windows Security Identifier?

A. Users

B. Servers

C. Groups

D. Only A and C above

E. All of the above

Answer: E

QUESTION NO: 8

The command _______ is used on a Samba 3 server to modify the SSID in an existing NT profile file called NTUser.DAT.

A. PROFILES

Answer: A

QUESTION NO: 9

What must be done to allow only users of the devel system group to access a share?

A. In the smb.conf file, set valid users = @devel

B. In the smb.conf file, set valid groups = @devel

C. In the smb.conf file, set valid groups = devel

D. chgrp the directory on the Samba server to the devel group, and then set the GID bit on the directory. A+ Exams

Answer: A

A+ Exams, CompTIA A+ Certification

QUESTION NO: 1

On a system running the K Display Manager, when is the /etc/kde4/kdm/Xreset script automatically executed?

A. When KDM starts
B. When a user's X session exists
C. When KDM crashes
D. When X is restarted
E. When X crashes

Answer: B

QUESTION NO: 2
What is the purpose of the Sticky Keys feature in X?

A. To assist users who have difficulty holding down multiple keys at once
B. To prevent repeated input of a single character if the key is held down
C. To ignore brief keystrokes according to a specified time limit
D. To repeat the input of a single character

Answer: A

QUESTION NO: 102

A department decided to change the Gnome Display Manager's greeting. Which of the following configuration files should an administrator edit?

A. /etc/gnome/greeting

B. /opt/gnome/share/greeting

C. /etc/X11/gmd.conf

D. /etc/X11/gdm/Init/Default

Answer: D

QUESTION NO: 3

Which of the following are commonly used Mail Transfer Agent (MTA) applications? (Select THREE).

A. postfix

B. procmail

C. sendmail

D. exim

E. smtpd

Answer: A,C,D

QUESTION NO: 4 CORRECT TEXT

Which file lists which users can execute commands using sudo? (Provide the full path and filename). A+ Exams

Answer: /ETC/SUDOERS